docs: accept ADR-0004, lessons and overlays arrive as Skills
Accepted by the owner on 2026-10-08 with its six decisions as written: a person approves every lesson; a lesson must be shown to help by evaluation; lessons are per Cloud provider; overlay Skills come only from configured directories; each Execution records the Skills it loaded; and lesson candidates are client data kept out of the repository. - CONTEXT.md gains Lesson candidate, Lesson and Overlay Skill. - Iteration 4 step 9 is complete; steps 10 and 12 name the decisions they must meet and are unblocked. Neither is built. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
This commit is contained in:
@@ -2,7 +2,7 @@
|
||||
|
||||
**Iteration:** 4, learning and Skills
|
||||
**Intent:** Make the agent a learning, adaptable solution through Skills. Fix the cheap defects the 2026-10-06 review found, then close the loop so each Execution can improve the next through a reviewed Skill change, then let new standards, clients and Cloud providers arrive as Skills and configuration.
|
||||
**Status:** steps 1 to 8, 11, 13 and 15 to 20 built; case 01 completed on them on 2026-10-07 (`../iter-06-target-architecture-graph/steps/step-11.md`); the other cases have not run, so no criterion is measured across the benchmark; step 9 drafted and awaiting the owner; steps 10, 12 and 14 planned. Steps 1 to 6 are in commit `7ee49ab`; the rest are uncommitted.
|
||||
**Status:** steps 1 to 8, 11, 13 and 15 to 20 built; case 01 completed on them on 2026-10-07 (`../iter-06-target-architecture-graph/steps/step-11.md`); the other cases have not run, so no criterion is measured across the benchmark; step 9 complete (ADR-0004 accepted 2026-10-08), which unblocks steps 10 and 12; steps 10, 12 and 14 planned. Steps 1 to 6 are in commit `7ee49ab`; the rest are uncommitted.
|
||||
**Changed by iteration 6:** `docs/adr/0005-the-target-architecture-is-an-explicit-graph.md` (accepted 2026-10-07) replaces the free-form `findings.json` of step 1 with a verdict per Check, remove the diagrammer, and add a Phase. Its plan is `../iter-06-target-architecture-graph/`, which lists the effect on each step here and should be built before steps 10 to 14.
|
||||
**This directory covers:** steps 1 to 24
|
||||
|
||||
@@ -25,7 +25,7 @@
|
||||
| 6 | Orchestrator step order | A | S | built; seen working in one stopped run, no completed evaluation |
|
||||
| 7 | Capture lesson candidates | B | M | complete |
|
||||
| 8 | Evaluation that can see improvement | B | M | built; thresholds and a judged run outstanding |
|
||||
| 9 | ADR: the lessons loop and overlay Skills | B | S | drafted as `docs/adr/0004-lessons-and-overlays-arrive-as-skills.md`, status proposed; awaits the owner |
|
||||
| 9 | ADR: the lessons loop and overlay Skills | B | S | complete: ADR-0004 accepted 2026-10-08 |
|
||||
| 10 | Lessons Skill and lesson curator | B | L | planned |
|
||||
| 11 | IaC patterns Skill | B | M | built; in case 01 the IaC author fell from 57 requests to 11 with no Revision; other cases unmeasured |
|
||||
| 12 | Overlay Skills and an organisation standards Skill | C | M | planned |
|
||||
|
||||