feat: a work breakdown structure with a computed timeline (iteration 10)
Some checks failed
validation / verify (push) Failing after 10s

A new Deliverable in the packaging Phase, produced by a delivery planner
after validation.

- The planner writes the plan as data: work packages that name the Elements
  they deliver, and activities with days, what each follows, and whether the
  team or the customer owns it.
- Code checks the plan against the design: every Element belongs to a work
  package, and the activities can be scheduled.
- Code computes the schedule, with no more of the team's activities at once
  than the team has people, and the critical path.
- Code writes the WBS dictionary (a work package is done when the Checks on
  its Elements pass), the activity sequence and a timeline on a relative axis
  from Day 0.
- The plan is checked against the delivery window from the agreed scope; over
  it, the Deliverable says by how much and names the critical path.
- With a start date it also gives calendar dates and a Mermaid Gantt chart.
- The timeline is added to the solution guide, and the plan's length is in
  execution.json and the packaging Approval.

Not run with real models.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
This commit is contained in:
2026-10-11 19:54:17 +01:00
parent 0f80cb642f
commit f54af24169
21 changed files with 1108 additions and 12 deletions

View File

@@ -15,7 +15,7 @@ One directory per iteration of this agent. Each holds the plan for that iteratio
| 7 | `iter-07-change-requests/` | complete (2026-10-09): the change case ran with real models and passed | A user restates a request to say how requirements changed; a new Execution starts from a Baseline Execution of the same Customer case and delivers the updated architecture with what changed. |
| 8 | `iter-08-terraform-modules/` | steps 1–5 built and run once each way on 2026-10-09, both at 100%; steps 6 and 7 wait on Azure and AWS provider bundles | Infrastructure code is plain resources by default. An Execution may opt into published Terraform modules: only from registry namespaces the provider bundle lists, at one exact version, with a lookup of what a module accepts and a Skill of four Google modules tested against the pinned provider. |
| 9 | `iter-09-scoping/` | steps 1–3 and 6 built on 2026-10-11; cases 03 and 08 ran on steps 1 and 2; steps 4 and 5 planned; ADR-0008 accepted | An engagement is scoped from a scope spec: a structured file, complete or partly filled, read against a catalogue in code, completed in conversation and approved before requirements begin. Covers workloads and platform foundations. |
| 10 | `iter-10-work-breakdown/` | planned; nothing built | A work breakdown structure as a Deliverable: work packages traced to Elements and Checks, activities in sequence, and a timeline on a relative day axis computed and drawn by code. |
| 10 | `iter-10-work-breakdown/` | steps 1–4 built on 2026-10-11, without milestones; not run with real models | A work breakdown structure as a Deliverable: work packages traced to Elements and Checks, activities in sequence, and a timeline on a relative day axis computed and drawn by code. |
Numbers record when an iteration was planned, not the order to build in. Build iteration 6 before the remaining steps of iteration 4 (10 to 14) and before iteration 5: it changes the Deliverables, Phases and validation format they build on. Its `MAP.md` lists the effect on each of their steps.