feat: a work breakdown structure with a computed timeline (iteration 10)
Some checks failed
validation / verify (push) Failing after 10s

A new Deliverable in the packaging Phase, produced by a delivery planner
after validation.

- The planner writes the plan as data: work packages that name the Elements
  they deliver, and activities with days, what each follows, and whether the
  team or the customer owns it.
- Code checks the plan against the design: every Element belongs to a work
  package, and the activities can be scheduled.
- Code computes the schedule, with no more of the team's activities at once
  than the team has people, and the critical path.
- Code writes the WBS dictionary (a work package is done when the Checks on
  its Elements pass), the activity sequence and a timeline on a relative axis
  from Day 0.
- The plan is checked against the delivery window from the agreed scope; over
  it, the Deliverable says by how much and names the critical path.
- With a start date it also gives calendar dates and a Mermaid Gantt chart.
- The timeline is added to the solution guide, and the plan's length is in
  execution.json and the packaging Approval.

Not run with real models.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
This commit is contained in:
2026-10-11 19:54:17 +01:00
parent 0f80cb642f
commit f54af24169
21 changed files with 1108 additions and 12 deletions

View File

@@ -0,0 +1,28 @@
# Steps 1 to 4 — Implementation Detail
Built on 2026-10-11. **Not run with real models.**
1. **A new Deliverable, `work_breakdown`,** in the packaging Phase, after validation, produced by a new Specialist, the delivery planner (`agents/delivery-planner.md`, on the larger model). It is given the Target architecture and the deployment guidance in full.
2. **The planner writes the plan as data,** `work-breakdown.json`: work packages (a hierarchy, each naming the Elements it delivers, its scope, what it produces and the skills it needs) and activities (work package, days, what each comes after, and whether the team or the customer owns it).
3. **Code checks the plan against the design** (`check_work_breakdown` in `app/workflows/work_breakdown.py`). A submission is refused when an Element belongs to no work package, a work package names an Element that does not exist, an activity follows one that does not exist, activities depend on each other in a circle, a duration is not above zero or is over 120 days, or a work package holds neither an activity nor another work package.
4. **Code computes the schedule** (`schedule`). An activity starts when everything it follows has finished. The team's activities also wait for a free person: no more run at once than the team has people, with the longest remaining chain placed first. What the customer owns takes nobody from the team. The critical path is every activity with no slack.
5. **Code writes the three views** into the Deliverable when it is submitted, as it writes the architecture's tables:
- the **WBS dictionary**, each work package with the Checks on its Elements as what makes it done, read from the Target architecture;
- the **activity sequence**, with each activity's start and finish day and whether it is critical;
- the **timeline**, a chart in text along a relative axis from Day 0, the team's work and the customer's drawn differently and the critical path marked.
6. **The delivery terms come from the agreed scope:** team size, working week, delivery window and start date. A team size the scope does not give is 2, and the Deliverable says it was assumed.
7. **The plan is checked against the delivery window.** Over it, the Deliverable says by how much and names the critical path. Nothing shortens an estimate to fit.
8. **What the customer owns is listed** with its lead time and the assumption behind it.
9. **With a start date in the scope** the activity sequence also gives calendar dates, skipping weekends, and a Mermaid Gantt chart is attached as `timeline.mmd`. Without one there are no dates to draw, and the text chart is the timeline.
10. **The guide carries the timeline.** The guide and the plan are produced side by side, so neither reads the other; when an Execution's files are written, the plan's timeline is added to the guide as "Delivery plan". `execution.json` records the plan's length, team, whether it fits the window and its critical path, and the packaging Approval says the same.
Differs from the spec:
- **Milestones for fixed-price work are not built.**
- **An assumption in the scope is not linked to an activity by id.** An activity the customer owns carries its own assumption as text.
- **The timeline chart is text.** A Mermaid Gantt chart needs dates, so one is drawn only when the scope gives a start date.
- **The guide does not depend on the plan.** Making it wait would have put the plan on the path of every Execution's last step; adding the timeline in code keeps them independent.
Durations are a model's estimates. The Deliverable says so.
Tests: `tests/execution/test_work_breakdown.py` (16).