A new Deliverable in the packaging Phase, produced by a delivery planner
after validation.
- The planner writes the plan as data: work packages that name the Elements
they deliver, and activities with days, what each follows, and whether the
team or the customer owns it.
- Code checks the plan against the design: every Element belongs to a work
package, and the activities can be scheduled.
- Code computes the schedule, with no more of the team's activities at once
than the team has people, and the critical path.
- Code writes the WBS dictionary (a work package is done when the Checks on
its Elements pass), the activity sequence and a timeline on a relative axis
from Day 0.
- The plan is checked against the delivery window from the agreed scope; over
it, the Deliverable says by how much and names the critical path.
- With a start date it also gives calendar dates and a Mermaid Gantt chart.
- The timeline is added to the solution guide, and the plan's length is in
execution.json and the packaging Approval.
Not run with real models.
Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
Case 08 named the customer's stated topology in its design and did not build
it; every Check passed because none asked for it.
- The catalogue marks the 26 fields that bind a design. The agreed scope lists
the ones the customer stated; what was assumed for them does not bind.
- A requirement says what it comes from. A submission of requirements is
refused when one of the customer's own requirements, or a stated binding
field, is named by none, or when the requirement carrying a choice is not a
constraint with a condition. The existing chain then owes it a Check.
- Generated code may use only the providers the bundle pins: a resource or a
required_providers entry of any other is refused before Terraform runs.
- The guide opens with how much of the design the customer stated, how much
was assumed and how much is unknown.
Not run with real models.
Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
Every Execution now begins by agreeing the scope, before requirements.
- A new Phase and Deliverable, produced by a scope analyst with two tools:
scope_read shows what is settled and what is not; scope_set records fields
with where each value came from (the request, the customer's answer, or an
assumption with its reason). Code checks each value against the catalogue.
- With someone present the analyst asks for what is missing; with nobody
present it assumes it, visibly. With no spec it drafts one from the request.
A value the customer stated in the file is changed only by their own answer.
- A submission cannot leave an essential field unknown. Code writes the
completed spec, the data every later Specialist reads, and the information
register, from what was recorded.
- The spec's status follows the Execution: under review, approved, then
locked as a Baseline. A Change request starts from the delivered scope.
- The requirements analyst derives from the agreed scope and no longer asks
for what it settles.
About 80 tests assumed requirements came first; tests/scoped.py runs scoping
ahead of a test's own script, and tests about order and counts are updated.
Not run with real models.
Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>