Commit Graph

6 Commits

Author SHA1 Message Date
f54af24169 feat: a work breakdown structure with a computed timeline (iteration 10)
Some checks failed
validation / verify (push) Failing after 10s
A new Deliverable in the packaging Phase, produced by a delivery planner
after validation.

- The planner writes the plan as data: work packages that name the Elements
  they deliver, and activities with days, what each follows, and whether the
  team or the customer owns it.
- Code checks the plan against the design: every Element belongs to a work
  package, and the activities can be scheduled.
- Code computes the schedule, with no more of the team's activities at once
  than the team has people, and the critical path.
- Code writes the WBS dictionary (a work package is done when the Checks on
  its Elements pass), the activity sequence and a timeline on a relative axis
  from Day 0.
- The plan is checked against the delivery window from the agreed scope; over
  it, the Deliverable says by how much and names the critical path.
- With a start date it also gives calendar dates and a Mermaid Gantt chart.
- The timeline is added to the solution guide, and the plan's length is in
  execution.json and the packaging Approval.

Not run with real models.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-11 19:54:17 +01:00
545097530b feat: scoping is the first Phase, completed in conversation (iteration 9 step 2)
Some checks failed
validation / verify (push) Failing after 10s
Every Execution now begins by agreeing the scope, before requirements.

- A new Phase and Deliverable, produced by a scope analyst with two tools:
  scope_read shows what is settled and what is not; scope_set records fields
  with where each value came from (the request, the customer's answer, or an
  assumption with its reason). Code checks each value against the catalogue.
- With someone present the analyst asks for what is missing; with nobody
  present it assumes it, visibly. With no spec it drafts one from the request.
  A value the customer stated in the file is changed only by their own answer.
- A submission cannot leave an essential field unknown. Code writes the
  completed spec, the data every later Specialist reads, and the information
  register, from what was recorded.
- The spec's status follows the Execution: under review, approved, then
  locked as a Baseline. A Change request starts from the delivered scope.
- The requirements analyst derives from the agreed scope and no longer asks
  for what it settles.

About 80 tests assumed requirements came first; tests/scoped.py runs scoping
ahead of a test's own script, and tests about order and counts are updated.
Not run with real models.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-11 18:17:32 +01:00
5adc911a82 feat: keep an unchanged description, list conditions, review coverage with Jev
After case 02 (completed at 100%, but with two Revisions of the Target
architecture for gaps validation found one pass at a time):

- A Deliverable stands while what it was written from is unchanged. The
  architecture description is written from the Elements and Relationships,
  so a Revision that only adds or rewords Checks no longer runs the describer.
- Non-functional requirements and recommendations list their conditions,
  one entry per separate thing that must be true; submission requires them.
- A coverage review at submission (JEV_COVERAGE_REVIEW, off by default):
  for each condition, Jev chooses which Check verifies it, or none. Asked as
  one broad yes-or-no per requirement it could not tell a complete design
  from one with known gaps; asked as a choice per condition it raised all
  four known gaps of case 02 and nothing on the complete graph. An opt-in
  live test (LIVE_JEV=1) repeats that.
- The validator is told to report every gap in its first pass.

Plans record the case 02 run and both forms of the review with figures.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-07 20:58:38 +01:00
5bb22d984e fixed multile issues
Some checks failed
validation / verify (push) Failing after 8s
2026-10-07 17:33:36 +01:00
e9246828b3 feat: establish the Target architecture as a graph before code
Design is now approved before any infrastructure code is written (ADR-0005).
A new target-architect Specialist produces one graph of Elements,
Relationships and Checks; the diagram is rendered from it, deployment
guidance must account for every Check, and validation gives a verdict per
Check. Requirements, components, products and recommendations carry ids in
data files, and a submission with a gap in the Requirements chain is refused.

Also in this commit:
- Customer cases group Executions, with an intent history per case
- lesson candidates are captured when an Execution ends
- evaluation gains chain, verdict, judged and interactive checks, and
  per-case thresholds
- Terraform providers are cached between checks
- the requirements analyst proposes defaults instead of asking
- the legacy-baseline case and the checks that only read it are removed
- ADR-0006 (Change requests) accepted; ADR-0004 and ADR-0007 proposed
- plans for iterations 4 to 7 under .agents/plans/

Unproven with a real model: no evaluation run has completed on this design.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-07 13:59:09 +01:00
7ee49ab352 latest refactoring
Some checks failed
validation / verify (push) Failing after 10s
2026-10-06 20:22:37 +01:00