feat: a work breakdown structure with a computed timeline (iteration 10)
A new Deliverable in the packaging Phase, produced by a delivery planner
after validation.

- The planner writes the plan as data: work packages that name the Elements
  they deliver, and activities with days, what each follows, and whether the
  team or the customer owns it.
- Code checks the plan against the design: every Element belongs to a work
  package, and the activities can be scheduled.
- Code computes the schedule, with no more of the team's activities at once
  than the team has people, and the critical path.
- Code writes the WBS dictionary (a work package is done when the Checks on
  its Elements pass), the activity sequence and a timeline on a relative axis
  from Day 0.
- The plan is checked against the delivery window from the agreed scope; over
  it, the Deliverable says by how much and names the critical path.
- With a start date it also gives calendar dates and a Mermaid Gantt chart.
- The timeline is added to the solution guide, and the plan's length is in
  execution.json and the packaging Approval.

Not run with real models.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-11 19:54:17 +01:00

1.5 KiB

Plan Map

Iteration: 10, Work breakdown structure Intent: Deliver a plan for building the Target architecture: work packages traced to its Elements and Checks, activities in sequence, and a timeline on a relative day axis that code computes and draws. Status: steps 1 to 4 built on 2026-10-11, without milestones; not run with real models This directory covers: steps 1 to 4

Sources of truth

  • .scratch/scoping-and-work-breakdown/spec.md, section "The work breakdown structure".
  • docs/adr/0005-the-target-architecture-is-an-explicit-graph.md: the ids it traces to.
  • Iteration 9 step 1: the scope spec's delivery section (team size, window, commercial model).

Status

Step What Status
1 The Deliverable, its Specialist and its data file; every Element in a work package, checked in code built 2026-10-11 (steps/step-1-to-4.md)
2 The schedule computed in code: start and finish day, critical path, team size as a limit built 2026-10-11 (steps/step-1-to-4.md)
3 The three views written by code: WBS dictionary, activity sequence list, timeline on a relative axis built 2026-10-11 (steps/step-1-to-4.md)
4 The delivery window checked; assumptions the plan depends on shown on the timeline; milestones built 2026-10-11, without milestones (steps/step-1-to-4.md)

Decisions the owner accepted on 2026-10-11: after validation, in the packaging Phase; grouped by component; the technical build only.