Files
gcp_solution_architecture_a…/.agents/plans/iter-10-work-breakdown/steps
Jonathan Boniface f54af24169
Some checks failed
validation / verify (push) Failing after 10s
feat: a work breakdown structure with a computed timeline (iteration 10)
A new Deliverable in the packaging Phase, produced by a delivery planner
after validation.

- The planner writes the plan as data: work packages that name the Elements
  they deliver, and activities with days, what each follows, and whether the
  team or the customer owns it.
- Code checks the plan against the design: every Element belongs to a work
  package, and the activities can be scheduled.
- Code computes the schedule, with no more of the team's activities at once
  than the team has people, and the critical path.
- Code writes the WBS dictionary (a work package is done when the Checks on
  its Elements pass), the activity sequence and a timeline on a relative axis
  from Day 0.
- The plan is checked against the delivery window from the agreed scope; over
  it, the Deliverable says by how much and names the critical path.
- With a start date it also gives calendar dates and a Mermaid Gantt chart.
- The timeline is added to the solution guide, and the plan's length is in
  execution.json and the packaging Approval.

Not run with real models.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-11 19:54:17 +01:00
..