The evaluation (both cases three times: report, results, spread, each run's Deliverables and lesson candidates) and the hand-off through the Orchestration engine (report, the document of links, both agents' kept files and records). Benchmark cases only, all fictional; no machine paths, and the links carry no signatures. Other runs stay ignored. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
367 lines
7.6 KiB
JSON
367 lines
7.6 KiB
JSON
{
|
|
"work_packages": [
|
|
{
|
|
"id": "WP-1",
|
|
"name": "Identity, Pipeline & State Foundation",
|
|
"parent": null,
|
|
"elements": [
|
|
"E-18",
|
|
"E-19",
|
|
"E-20",
|
|
"E-21",
|
|
"E-22",
|
|
"E-23",
|
|
"E-24",
|
|
"E-25",
|
|
"E-26",
|
|
"E-31",
|
|
"E-54",
|
|
"E-55"
|
|
],
|
|
"scope": "Centralised identity, GitHub Actions pipeline authentication, Terraform state, and KMS encryption foundations.",
|
|
"produces": [
|
|
"WIF pipeline identity",
|
|
"TF state bucket",
|
|
"KMS rings",
|
|
"Audit log sink"
|
|
],
|
|
"skills": [
|
|
"security engineering",
|
|
"DevOps"
|
|
]
|
|
},
|
|
{
|
|
"id": "WP-2",
|
|
"name": "Resource Hierarchy & Guardrails",
|
|
"parent": null,
|
|
"elements": [
|
|
"E-1",
|
|
"E-2",
|
|
"E-3",
|
|
"E-27",
|
|
"E-28",
|
|
"E-29",
|
|
"E-30",
|
|
"E-38",
|
|
"E-46",
|
|
"E-56",
|
|
"E-57"
|
|
],
|
|
"scope": "Google Cloud folder structure for environment tiers and preventative organization policies.",
|
|
"produces": [
|
|
"Development, Staging, and Production folders",
|
|
"Organizational policies",
|
|
"SCC monitoring"
|
|
],
|
|
"skills": [
|
|
"cloud architecture",
|
|
"security engineering"
|
|
]
|
|
},
|
|
{
|
|
"id": "WP-3",
|
|
"name": "Network Fabric",
|
|
"parent": null,
|
|
"elements": [
|
|
"E-4",
|
|
"E-5",
|
|
"E-6",
|
|
"E-7",
|
|
"E-8",
|
|
"E-37",
|
|
"E-40",
|
|
"E-41",
|
|
"E-42",
|
|
"E-43",
|
|
"E-44",
|
|
"E-45",
|
|
"E-47",
|
|
"E-51",
|
|
"E-52",
|
|
"E-53"
|
|
],
|
|
"scope": "The Shared VPC host project, hub-and-spoke networks, subnets, peerings, and baseline routing.",
|
|
"produces": [
|
|
"Hub network",
|
|
"Spoke networks for all tiers",
|
|
"VPC peerings",
|
|
"Firewall rules"
|
|
],
|
|
"skills": [
|
|
"network engineering"
|
|
]
|
|
},
|
|
{
|
|
"id": "WP-4",
|
|
"name": "Traffic Inspection Gateway",
|
|
"parent": null,
|
|
"elements": [
|
|
"E-13",
|
|
"E-14",
|
|
"E-15",
|
|
"E-16",
|
|
"E-17"
|
|
],
|
|
"scope": "The Network Virtual Appliance (NVA) managed instance group for egress inspection.",
|
|
"produces": [
|
|
"NVA MIG",
|
|
"Internal Load Balancer for egress"
|
|
],
|
|
"skills": [
|
|
"network engineering",
|
|
"security engineering"
|
|
]
|
|
},
|
|
{
|
|
"id": "WP-5",
|
|
"name": "Hybrid Interconnect",
|
|
"parent": null,
|
|
"elements": [
|
|
"E-9",
|
|
"E-10",
|
|
"E-11",
|
|
"E-12",
|
|
"E-35",
|
|
"E-36"
|
|
],
|
|
"scope": "Cloud Routers and VLAN attachments for the 10Gbps Dedicated Interconnect.",
|
|
"produces": [
|
|
"Primary Cloud Routers",
|
|
"Standby Cloud Router",
|
|
"VLAN attachments"
|
|
],
|
|
"skills": [
|
|
"network engineering"
|
|
]
|
|
},
|
|
{
|
|
"id": "WP-6",
|
|
"name": "Telemetry & Validation",
|
|
"parent": null,
|
|
"elements": [
|
|
"E-32",
|
|
"E-33",
|
|
"E-58"
|
|
],
|
|
"scope": "Alerting policies and environment-by-environment validation runs.",
|
|
"produces": [
|
|
"Monitoring alerts",
|
|
"Validated landing zone"
|
|
],
|
|
"skills": [
|
|
"DevOps",
|
|
"cloud engineering"
|
|
]
|
|
}
|
|
],
|
|
"activities": [
|
|
{
|
|
"id": "A-1",
|
|
"work_package": "WP-1",
|
|
"name": "Enable provider APIs and bootstrap initial state bucket",
|
|
"days": 1,
|
|
"after": []
|
|
},
|
|
{
|
|
"id": "A-2",
|
|
"work_package": "WP-1",
|
|
"name": "Configure Cloud KMS key rings and crypto keys",
|
|
"days": 1,
|
|
"after": [
|
|
"A-1"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-3",
|
|
"work_package": "WP-1",
|
|
"name": "Deploy centralized audit log bucket and sink",
|
|
"days": 1,
|
|
"after": [
|
|
"A-2"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-4",
|
|
"work_package": "WP-1",
|
|
"name": "Configure Workload Identity Federation & CI/CD service account",
|
|
"days": 2,
|
|
"after": [
|
|
"A-1"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-5",
|
|
"work_package": "WP-1",
|
|
"name": "Provision Cloud Identity groups",
|
|
"days": 0.5,
|
|
"after": [
|
|
"A-1"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-6",
|
|
"work_package": "WP-1",
|
|
"name": "Set up GitHub Actions pipeline for infrastructure deployment",
|
|
"days": 2,
|
|
"after": [
|
|
"A-4"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-7",
|
|
"work_package": "WP-2",
|
|
"name": "Provision environment folders (Dev, Staging, Prod)",
|
|
"days": 1,
|
|
"after": [
|
|
"A-6"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-8",
|
|
"work_package": "WP-2",
|
|
"name": "Implement organizational policies and constraints",
|
|
"days": 2,
|
|
"after": [
|
|
"A-7"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-9",
|
|
"work_package": "WP-2",
|
|
"name": "Configure Security Command Center custom modules",
|
|
"days": 1,
|
|
"after": [
|
|
"A-7"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-10",
|
|
"work_package": "WP-3",
|
|
"name": "Provision host project and baseline VPC networks",
|
|
"days": 2,
|
|
"after": [
|
|
"A-7"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-11",
|
|
"work_package": "WP-3",
|
|
"name": "Establish VPC peerings between hub and spokes",
|
|
"days": 1,
|
|
"after": [
|
|
"A-10"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-12",
|
|
"work_package": "WP-3",
|
|
"name": "Configure subnetworks across primary and secondary regions",
|
|
"days": 2,
|
|
"after": [
|
|
"A-10"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-13",
|
|
"work_package": "WP-3",
|
|
"name": "Implement centralized firewall rules and routing",
|
|
"days": 2,
|
|
"after": [
|
|
"A-11",
|
|
"A-12"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-14",
|
|
"work_package": "WP-4",
|
|
"name": "Create NVA instance templates and health checks",
|
|
"days": 1,
|
|
"after": [
|
|
"A-12"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-15",
|
|
"work_package": "WP-4",
|
|
"name": "Deploy NVA Managed Instance Group and autoscaler",
|
|
"days": 2,
|
|
"after": [
|
|
"A-14"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-16",
|
|
"work_package": "WP-4",
|
|
"name": "Configure NVA internal load balancer",
|
|
"days": 1,
|
|
"after": [
|
|
"A-15"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-17",
|
|
"work_package": "WP-5",
|
|
"name": "Order and provision the dedicated carrier circuit",
|
|
"days": 30,
|
|
"after": [],
|
|
"owner": "customer",
|
|
"assumption": "The customer manages the carrier's lead time for physical circuit delivery."
|
|
},
|
|
{
|
|
"id": "A-18",
|
|
"work_package": "WP-5",
|
|
"name": "Provision Cloud Interconnect Routers",
|
|
"days": 1,
|
|
"after": [
|
|
"A-10"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-19",
|
|
"work_package": "WP-5",
|
|
"name": "Configure VLAN attachments and establish BGP",
|
|
"days": 2,
|
|
"after": [
|
|
"A-17",
|
|
"A-18"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-20",
|
|
"work_package": "WP-6",
|
|
"name": "Configure infrastructure alerting policies",
|
|
"days": 2,
|
|
"after": [
|
|
"A-16",
|
|
"A-19"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-21",
|
|
"work_package": "WP-6",
|
|
"name": "Run validation in Development environment",
|
|
"days": 1,
|
|
"after": [
|
|
"A-20"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-22",
|
|
"work_package": "WP-6",
|
|
"name": "Run validation in Staging environment",
|
|
"days": 1,
|
|
"after": [
|
|
"A-21"
|
|
]
|
|
},
|
|
{
|
|
"id": "A-23",
|
|
"work_package": "WP-6",
|
|
"name": "Run validation in Production environment",
|
|
"days": 1,
|
|
"after": [
|
|
"A-22"
|
|
]
|
|
}
|
|
]
|
|
} |