Files
Jonathan Boniface 628b6ee170 docs: publish the runs of 2026-10-21
The evaluation (both cases three times: report, results, spread, each
run's Deliverables and lesson candidates) and the hand-off through the
Orchestration engine (report, the document of links, both agents' kept
files and records). Benchmark cases only, all fictional; no machine paths,
and the links carry no signatures. Other runs stay ignored.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-10-22 09:25:03 +01:00

367 lines
7.6 KiB
JSON

{
"work_packages": [
{
"id": "WP-1",
"name": "Identity, Pipeline & State Foundation",
"parent": null,
"elements": [
"E-18",
"E-19",
"E-20",
"E-21",
"E-22",
"E-23",
"E-24",
"E-25",
"E-26",
"E-31",
"E-54",
"E-55"
],
"scope": "Centralised identity, GitHub Actions pipeline authentication, Terraform state, and KMS encryption foundations.",
"produces": [
"WIF pipeline identity",
"TF state bucket",
"KMS rings",
"Audit log sink"
],
"skills": [
"security engineering",
"DevOps"
]
},
{
"id": "WP-2",
"name": "Resource Hierarchy & Guardrails",
"parent": null,
"elements": [
"E-1",
"E-2",
"E-3",
"E-27",
"E-28",
"E-29",
"E-30",
"E-38",
"E-46",
"E-56",
"E-57"
],
"scope": "Google Cloud folder structure for environment tiers and preventative organization policies.",
"produces": [
"Development, Staging, and Production folders",
"Organizational policies",
"SCC monitoring"
],
"skills": [
"cloud architecture",
"security engineering"
]
},
{
"id": "WP-3",
"name": "Network Fabric",
"parent": null,
"elements": [
"E-4",
"E-5",
"E-6",
"E-7",
"E-8",
"E-37",
"E-40",
"E-41",
"E-42",
"E-43",
"E-44",
"E-45",
"E-47",
"E-51",
"E-52",
"E-53"
],
"scope": "The Shared VPC host project, hub-and-spoke networks, subnets, peerings, and baseline routing.",
"produces": [
"Hub network",
"Spoke networks for all tiers",
"VPC peerings",
"Firewall rules"
],
"skills": [
"network engineering"
]
},
{
"id": "WP-4",
"name": "Traffic Inspection Gateway",
"parent": null,
"elements": [
"E-13",
"E-14",
"E-15",
"E-16",
"E-17"
],
"scope": "The Network Virtual Appliance (NVA) managed instance group for egress inspection.",
"produces": [
"NVA MIG",
"Internal Load Balancer for egress"
],
"skills": [
"network engineering",
"security engineering"
]
},
{
"id": "WP-5",
"name": "Hybrid Interconnect",
"parent": null,
"elements": [
"E-9",
"E-10",
"E-11",
"E-12",
"E-35",
"E-36"
],
"scope": "Cloud Routers and VLAN attachments for the 10Gbps Dedicated Interconnect.",
"produces": [
"Primary Cloud Routers",
"Standby Cloud Router",
"VLAN attachments"
],
"skills": [
"network engineering"
]
},
{
"id": "WP-6",
"name": "Telemetry & Validation",
"parent": null,
"elements": [
"E-32",
"E-33",
"E-58"
],
"scope": "Alerting policies and environment-by-environment validation runs.",
"produces": [
"Monitoring alerts",
"Validated landing zone"
],
"skills": [
"DevOps",
"cloud engineering"
]
}
],
"activities": [
{
"id": "A-1",
"work_package": "WP-1",
"name": "Enable provider APIs and bootstrap initial state bucket",
"days": 1,
"after": []
},
{
"id": "A-2",
"work_package": "WP-1",
"name": "Configure Cloud KMS key rings and crypto keys",
"days": 1,
"after": [
"A-1"
]
},
{
"id": "A-3",
"work_package": "WP-1",
"name": "Deploy centralized audit log bucket and sink",
"days": 1,
"after": [
"A-2"
]
},
{
"id": "A-4",
"work_package": "WP-1",
"name": "Configure Workload Identity Federation & CI/CD service account",
"days": 2,
"after": [
"A-1"
]
},
{
"id": "A-5",
"work_package": "WP-1",
"name": "Provision Cloud Identity groups",
"days": 0.5,
"after": [
"A-1"
]
},
{
"id": "A-6",
"work_package": "WP-1",
"name": "Set up GitHub Actions pipeline for infrastructure deployment",
"days": 2,
"after": [
"A-4"
]
},
{
"id": "A-7",
"work_package": "WP-2",
"name": "Provision environment folders (Dev, Staging, Prod)",
"days": 1,
"after": [
"A-6"
]
},
{
"id": "A-8",
"work_package": "WP-2",
"name": "Implement organizational policies and constraints",
"days": 2,
"after": [
"A-7"
]
},
{
"id": "A-9",
"work_package": "WP-2",
"name": "Configure Security Command Center custom modules",
"days": 1,
"after": [
"A-7"
]
},
{
"id": "A-10",
"work_package": "WP-3",
"name": "Provision host project and baseline VPC networks",
"days": 2,
"after": [
"A-7"
]
},
{
"id": "A-11",
"work_package": "WP-3",
"name": "Establish VPC peerings between hub and spokes",
"days": 1,
"after": [
"A-10"
]
},
{
"id": "A-12",
"work_package": "WP-3",
"name": "Configure subnetworks across primary and secondary regions",
"days": 2,
"after": [
"A-10"
]
},
{
"id": "A-13",
"work_package": "WP-3",
"name": "Implement centralized firewall rules and routing",
"days": 2,
"after": [
"A-11",
"A-12"
]
},
{
"id": "A-14",
"work_package": "WP-4",
"name": "Create NVA instance templates and health checks",
"days": 1,
"after": [
"A-12"
]
},
{
"id": "A-15",
"work_package": "WP-4",
"name": "Deploy NVA Managed Instance Group and autoscaler",
"days": 2,
"after": [
"A-14"
]
},
{
"id": "A-16",
"work_package": "WP-4",
"name": "Configure NVA internal load balancer",
"days": 1,
"after": [
"A-15"
]
},
{
"id": "A-17",
"work_package": "WP-5",
"name": "Order and provision the dedicated carrier circuit",
"days": 30,
"after": [],
"owner": "customer",
"assumption": "The customer manages the carrier's lead time for physical circuit delivery."
},
{
"id": "A-18",
"work_package": "WP-5",
"name": "Provision Cloud Interconnect Routers",
"days": 1,
"after": [
"A-10"
]
},
{
"id": "A-19",
"work_package": "WP-5",
"name": "Configure VLAN attachments and establish BGP",
"days": 2,
"after": [
"A-17",
"A-18"
]
},
{
"id": "A-20",
"work_package": "WP-6",
"name": "Configure infrastructure alerting policies",
"days": 2,
"after": [
"A-16",
"A-19"
]
},
{
"id": "A-21",
"work_package": "WP-6",
"name": "Run validation in Development environment",
"days": 1,
"after": [
"A-20"
]
},
{
"id": "A-22",
"work_package": "WP-6",
"name": "Run validation in Staging environment",
"days": 1,
"after": [
"A-21"
]
},
{
"id": "A-23",
"work_package": "WP-6",
"name": "Run validation in Production environment",
"days": 1,
"after": [
"A-22"
]
}
]
}